| 1 |
18835046-RU-SO |
ADOQUÍN VEHICULAR HEXAGONAL 20/M2... |
1128 |
Metro Cuadrado |
27.76 |
ADOQUINES HEXAGONALES DE CONCRETO 400 KG... |
| 2 |
18835050-RU-SO |
DESALOJODE MATERIAL HASTA 3KM. CARGADOMA... |
104 |
Metro Cúbico |
1.61 |
LIMPIEZA DE SEDIMENTOS |
| 3 |
18835049-RU-SO |
RELLENO COMP. MECANICO CON MATERIAL DE M... |
226 |
Metro Cúbico |
24.06 |
RELLENOS |
| 4 |
18835048-RU-SO |
LETREROS INFORMATIVOS |
1 |
Unidad |
51.57 |
CARTELERAS |
| 5 |
18835047-RU-SO |
CUNETAS LATERALES H.S. 210 KG/CM2 |
384 |
Metro |
22.38 |
HORMIGON PREMEZCLADO |
| 6 |
18835006-RU-SO |
COLCHON DE ARENA E=7CM |
93 |
Metro Cúbico |
1.61 |
MATERIALES Y ACABADOS DE CONSTRUCCION |
| 7 |
18835005-RU-SO |
HORMIGÓN CICLÓPEOF 'C= 180... |
44 |
Metro Cúbico |
189.65 |
HORMIGON PREMEZCLADO |
| 8 |
18835004-RU-SO |
BERMAS DE SECCIÓN 0.20x0.40m, HS... |
11 |
Metro Cúbico |
261.90 |
HORMIGON PREMEZCLADO |
| 9 |
18835003-RU-SO |
BORDILLO DE SECCIÓN 0.15X0.20X0.5... |
34 |
Metro Cúbico |
246.42 |
HORMIGON PREMEZCLADO |
| 10 |
18835002-RU-SO |
EXCAVACIONMANUAL PARA ESTRUCTURAS MENORE... |
152 |
Metro Cúbico |
5.48 |
EXCAVACION DE ZANJAS |
| 11 |
18835001-RU-SO |
ALZADA DE CUELLOS DE POZOS |
6 |
Unidad |
41.54 |
HORMIGON PREMEZCLADO |
| 12 |
18835000-RU-SO |
REPLANTEO Y NIVELACION CON EQUIPOS TOPOG... |
1396 |
Metro Cuadrado |
0.38 |
NIVELACION DE EMPLAZAMIENTOS |
| 13 |
18834999-RU-SO |
LIMPIEZA PRELIMINAR DE LA OBRA |
1396 |
Metro Cuadrado |
0.05 |
LIMPIEZA DE SEDIMENTOS |
| 14 |
18834998-RU-SO |
LIMPIEZA FINAL DE LA OBRA (gbl) |
1 |
Unidad |
54.68 |
LIMPIEZA DE SEDIMENTOS |
| 15 |
18834997-RU-SO |
CINTA DE SEGURIDAD |
50 |
Metro |
1.22 |
CINTA DE SEGURIDAD |